A PERT (Project Evaluation and Review Technique) flow chart helps in identifying the most consecutive dependent tasks through its critical path component. The critical path is the sequence of tasks that must be completed in a specific order for the project to be completed in the shortest possible time. It's the longest path through the project, and any delay in any of the tasks on the critical path directly impacts the project's completion date. Therefore, by visualizing the critical path on the PERT chart, one can easily identify the most consecutive dependent tasks.